Progress continues on construction of the new elementary school at the Ridgeview complex. As of the school board’s late January meeting, interior masonry work was finished and exterior brick work had started. Electrical and HVAC rough-in work was underway and site utility work was completed. The roughly $24.56 million project is expected to be finished by September.  JEFF LESTER PHOTO


%> "